Switzerland County, IN — Milestone Contractors, L.P. plans to implement full closures along State Road 129 starting this week in Switzerland County to perform subgrade stabilization work as part of an $11 million full-depth pavement reclamation contract that began earlier this year.
The road closed to thru traffic between Pleasant and Vevay in April, but local access has been maintained for residents in the area. During upcoming work, sections of State Road 129 will be closed to all traffic for work to take place across both lanes of the highway. Closures are scheduled as follows, but may change based on weather and other factors:
Wednesday, June 30 to Friday, July 2 (7 a.m. to 6 p.m.): S.R. 129 closed to all traffic between Glen Roberts Road and Martin Road
Tuesday, July 6 to Saturday, July 10 (7 a.m. to 6 p.m.): S.R. 129 closed to all traffic between Glen Roberts Road and Martin Road
Monday, July 12 to Saturday, July 17 (7 a.m. to 6 p.m.): S.R. 129 closed to all traffic between Bursot Road and Long Run Road
Monday, July 19 to Saturday, July 24 (7 a.m. to 6 p.m.): S.R. 129 closed to all traffic between Bursot Road and Long Run Road
The contract is currently expected to be complete by late September. The official detour will continue to follow State Road 56 and State Road 250.
Motorists are reminded to slow down, use extra caution, and drive distraction-free in and near construction zones. All work is weather-dependent and schedules are subject to change.