Dave O’Mara, INDOT’s contractor, plans to begin patching operations in early May. The contract’s completion date is September 30.
This $1.9 million project calls for the contractor to mill and replace 1½ inches of existing asphalt pavement after completing full- and partial-depth patching. Road and drive approaches will be paved. A sinusoidal wave will function along the centerline to warn drivers of cross-lane hazards.
The U.S. 50 resurfacing project will end just west of this summer’s roundabout construction at the U.S. 50/Walnut Street-CR 400 West interchange, two miles west of North Vernon.
U.S. 50 has a traffic count of 12,980 vehicles per day.