The first task for work crews will be constructing temporary crossovers in order to maintain traffic during the project.
Crown Point, Indiana-based Walsh Construction has the $16,790,126 to complete a concrete-over-asphalt resurfacing project’ Crews will also place cross-median asphalt lanes on U.S. 50 at either end of the project limits.
The contract calls for asphalt and concrete patching, construction of new driveway and road/street approaches—and a 4½-inch concrete overlay atop the existing asphalt base.
The 4.56 mile section of U.S. 50 to be white-topped begins 1.85 miles east of S.R. 262 and ends 2.44 miles west of S.R. 350. Motorists will experience single-lane traffic in both directions on the north side of the roadway beginning in April.
The project has a completion date of November 15.
Daily traffic count is 13,490 vehicles per day.