The lane width through the State Road 56 construction zone is 10 feet.
The $3.7 million project includes replacing the north half or westbound side of the Tucker Run structure while motorists are routed to the south half.
The 3-span concrete bulb-T bridge at Tucker Run measuring 200 feet in length with 33 feet of clear roadway side-to-side is tentatively scheduled to open to traffic in November, 2019.
A second State Road 56 bridge located less than a mile west of the Tucker Run structure will be removed and replaced after the first of the year. The new State Road 56 bridge at Green Valley Creek will be a single-span I-beam structure measuring 68 feet in length and 30 feet side-to-side.
Clearing is underway. Utility relocations will follow.
State Road 56 will be realigned at the Green Valley bridge site—allowing continuous free-flow traffic until pavement tie-ins occur. At that time, a 14-day closure will be imposed.
State Road 56’s traffic count is 2,257 vehicles per day.