A state highway detour routes motorists around the site via U.S. 421 and State Road 62.
Geostablization International, INDOT’s slide mitigation contractor, will embed 20-foot-long steel shafts into the slide area which measures 900 feet side-to-side and eight to 11 feet in height. Ends of these “soil nails” will be fitted with a wire mesh, then overcoated with shotcrete to form a stabilizing wall. The $1 million project also calls for pavement replacement and installation of curbs and gutters.
State Road 250 at the slide site has a traffic count of 780 vehicles per day.