Milan, IN— INDOT contractor Force Construction plans to close the S.R. 101 bridge over South Hogan Creek in Ripley County on or after Monday, June 1, for a deck replacement project. The road will close for approximately 90 days between C.R. 50 N. and C.R. 50 S., south of Milan, while work is completed.
The official detour for the closure will follow S.R. 350 to S.R. 129 to U.S. 50. The contract was awarded to Force Construction and is expected to be complete by September 30, 2020.