Crews will complete repairs on two structures, located approximately 7.5 miles and 6 miles north of S.R. 229, near C.R. 400 S. Work will take place on both structures simultaneously. In addition to the temporary signals and 45 mph speed restriction, a 12-foot width limit will also be in effect.
The contract was awarded in September 2019 and is expected to be complete by June 30, 2020. Motorists should slow down, watch for stopped traffic and drive distraction-free through all work zones. All work is weather dependent.