More Batesville streets being resurfaced this week

Batesville, IN—Starting Tuesday, 8/13, Globe Asphalt will be milling the following streets in the listed order:

Pheasant Run (from Wessel Rd to Six Pine Ranch)
Arlington Dr (from Northside Dr to Pocket Rd)
Little Leaf Lane (from Winding Way to White Oak Dr)
White Oak Dr (from short of Hawthorn Ct to the North into Cul-da-sac)

Starting Wednesday, 8/14 and Thursday, 8/15 they will be paving the streets in the same sequence as milling.

Paving may be delayed due to State paving time of S.R. 229 from I-74 to just past Northside the same day.