Franklin County, In. — Repairs to the Big Cedar Road embankment in Franklin County are set to be complete before August 31. The embankment was damaged by flooding in 2016 and original contract to make repairs in 2017 was delayed by state federal agencies.
Batesville-based All American Construction and Contracting will complete the work for an estimated $44,286.
The work must be complete by August 31 in order to qualify for a $140,000 government grant. The county share of the project cost is $35,000.