Next, crews will set concrete barrier wall sections—weather permitting—on Friday, November 30. Then excavation on an eroding slope just west of Western Creek will begin in preparation for slide correction measures by a specialty geohazard subcontractor.
Crews from Geostablization International are scheduled to begin work at Western Creek Monday, December 3. They will stabilize the slope with “soil nails” driven into bedrock. Metal gridwork attached to these steel shafts will be overcoated with shotcrete—forming a substantial retaining wall.
Once this embankment is stabilized, all I-74 lanes will remain open for winter travel until Phase III operations begin next spring.