Roadwork coming to Brookville

Road WorkBROOKVILLE, Ind. — Extensive roadwork is coming to Brookville.

INDOT says that construction signs may be put in place this week for the $2,739,500 project that is expected to impact vehicular and pedestrian traffic on US52/Main Street.

After signs are put in place, preparation operations are expected to begin.

The contract calls for extensive roadbed repairs, pavement milling, and placement of new asphalt surface lifts.

The contractor will also construct new sidewalks, curbs, and ADA-compliant curb ramps. Decorative street lighting will also be installed as part of the project.

The completion date is currently scheduled for October 13.